Wednesday, October 6, 2010
Wednesday, September 15, 2010
Training on the Medium Voltage Switchgear at Prkng Lt 4.
Cutler Hammer / Eaton Rep "Jun"
12KV Switch Gear Pkng Lt 4
- Schedule Preventative Maintenance
Batteries check hygrometer monthly
Start Log Keeping process
Schedule period of inspections of erosion indicators.
- Missing parts include
racking handle
charging handle
extension rails
- We need a hard copy of the manual to leave in battery compartment
menu guide for fault indicators on site
- Correction needed
Create as built Hi Voltage Single Line Diagram
Correct Bunker exposed Hi Voltage connections
amp meter calibrated for 1200 amps when we use less than 30 amp
Wednesday, February 3, 2010
swim pool gfi lights